31 Jan 2019
|
7 out 10 pier arms for concourse level of Phugewadi metro station completed for Pune Metro Reach 1 PCMC-Range Hill
|
28 Jan 2019
|
MoU of Rs 2000 Cr has been signed between Maha Metro & AFD_France
|
17 Jan 2019
|
Spans using 771 segments ready for Pune Metro Reach1 PCMC-Range Hills, 197 pillars with 124 pier caps are completed. 257 footings are done.
|
02 Jan 2019
|
Foundation for 192 pillars completed for Pune Metro Reach 2 Vanaz to Civil Court, 131 pillars are erected with 65 pier caps ready and total 132 segments are launched.
|
31 Dec 2018
|
First Pile cap completed for Reach 3 Civil Court to Ramwadi near Kutumb Kalyan Kendra.
|
17 Dec 2018
|
Pier arm work for Phugewadi metro station of Pune Metro Reach 1 PCMC-Range Hill has started. First three pier arm work is in progress.
|
13 Dec 2018
|
3 piling rigs operational to speed up the pillar foundation work for Pune Metro Reach 3 Civil Court to Ramwadi.
|
11 Dec 2018
|
36 out of 60 footings are completed at riverbed of Pune Metro Reach 2 Vanaz to Civil Court. 15 piers are ready for metro station & viaduct. Excavation & reinforcement work for the remaining piers is in progress.
|
04 Dec 2018
|
1083 viaduct segments are casted & stacked at casting yard for Pune Metro Reach1 PCMC - Range Hills.
|
29 Nov 2018
|
Pune Metro started foundation work for Double Layer Flyover at Nal Stop for Reach 2 Vanaz to Civil Court.
|
20 Nov 2018
|
For Sant Tukaram Nagar station of Reach1 PCMC-Range Hills, 7 out of 10 pier arms for concourse level are ready. Shuttering in progress for other 3.
|
19 Nov 2018
|
GeoTech work started on Nagar Road for PuneMetro Reach3 Civil Court to Ramwadi
|
16 Nov 2018
|
Bhoomipujan ceremony for the Karve Road double layer flyover was performed at the hands of Hon. CM Shri. Devendraji Fadnavis.
|
13 Nov 2018
|
12 spans comprising of 120 segments are ready from Mega Mart to CME gate at Phugewadi for Reach1 PCMC to Range Hills
|
06 Nov 2018
|
1000th Segment cast at Nashik Phata casting yard for Reach1 PCMC-RangeHills
|
01 Nov 2018
|
Piers near Paud Phata are ready for viaduct segments launch. Span formation curve at Anand Nagar. Along with station work on Pune Metro Reach2 Vanaz-Civil Court, erection of piers in progress near Vanaz Depot.
|
31 Oct 2018
|
First two pier arms of Ideal Colony station on Pune Metro Reach2 Vanaz-Civil Court route is in progress.
|
22 Oct 2018
|
3rd Launching Girder installed for Pune Metro work for Reach1 PCMC-Range Hils. Span formation work near Phugewadi, opposite to Sandvik Asia Ltd. to gain speed for the construction of viaduct.
|
21 Oct 2018
|
Total 949 precast segments casted & stacked at casting yard for Pune Metro Reach 1 PCMC - Range Hills. Out of total, 459 segments are launched to form 45 spans of the viaduct.
|
19 Oct 2018
|
Pune Metro #Reach2 Vanaz-Civil Court work in progress from Kinara Hotel to Kothrud Depot. Foundation for 145 pillars completed. 73 pillars are erected with 37 pier caps ready. Total 72 segments are launched.
|
15 Oct 2018
|
Civil work for Pune Metro Reach 3 Civil Court to Ramwadi has started. Concreting of first pile is completed at Raja Bahadur Mill Road.
|
12 Oct 2018
|
Pune Metro Reach1 PCMC-Range Hills - 3 out 10 pier arms for concourse level for Sant Tukaram Nagar metro station completed.
|
09 Oct 2018
|
Barricading has been done at various places along Pune Railway Station, Raja Bahadur Mill Road till Bund Garden for Pune Metro Reach3 - Civil Court to Ramwadi GeoTech work.
|
04 Oct 2018
|
Site visit by Dr. Brijesh Dixit, MD Maha Metro along with Pune Metro officials at casting yards of both Reach1 & 2. Work was inspected for quality, safety & workers were instructed to speed up work.
|
28 Sep 2018
|
Another record feat by Pune Metro by forming 15 spans by launching girder & work reached near Haffkin Institute, Pimpri for Reach1 PCMC-Range Hills. At the same time, 32 segments launched at Phugewadi. Piling operation in progress for Bhosari Metro station.
|
24 Sep 2018
|
Erection of pillars for proposed Pune Metro Anand Nagar & Vanaz stations are in progress
|
23 Sep 2018
|
With the help of Ground Support Trestle, 1st span completed at Phugewadi, opposite to Sandvik Asia Ltd. for Pune Metro Reach 1 PCMC- Range Hills. Soon the 3rd launching girder will be installed here.
|
20 Sep 2018
|
Pune Metro Samvaad conducted at Pune MahaNagarpalika Kamgaar Unions Shramik Sabhagruha Pune.
|
16 Sep 2018
|
1st span completed with the help of Ground Support Trestle at Phugewadi, opposite to Sandvik Asia Ltd. for Pune Metro Reach 1 PCMC- Range Hills.
|
15 Sep 2018
|
Piling operation for PuneMetro underground route ShivajiNagar-Swargate is completed at Agriculture College ground Total 144 piles, ~6 mtrs deep are done.
|
14 Sep 2018
|
PuneMetro progress update of Reach2 Vanaz-Civil Court 13 pillars foundation completed & work on 11 piers in progress near Garware College. 4 spans completed at Anand Nagar & pillar work started near Kachra Depot. Maximum stretch of Paud road is barricaded.
|
11 Sep 2018
|
Area from PCMC to Mother Teresa (Empire Estate) flyover is barricaded for civil work of PuneMetro Reach1 PCMC-RangeHills.
|
10 Sep 2018
|
Ongoing PuneMetro work for Reach1 PCMC-Range Hills is now started at Bopodi. Barricades erected on the alignment route opposite Kundan spaces.
|
08 Sep 2018
|
Pune Metro Samvaad conducted at Dnyaneshwar Mangal Karyalay, 1435, Shukrawar Peth, Near Mahatma Phule Mandai, Pune.
|
05 Sep 2018
|
Traffic & Road Safety awareness campaign by PuneMetro at Karve road & Nashik Phata
|
04 Sep 2018
|
Barricading at places on Raja Bahadur Mill Road and Bund Garden Road for PuneMetro Reach3 Civil Court to Ramwadi geotech survey in progress & the civil work is expected to start soon.
|
01 Sep 2018
|
PuneMetro Reach2 work of 4th span with help of Launching Girder in progress at Anand Nagar in day-night shift Total 10 segments are lifted in 2 days.
|
31 Aug 2018
|
Joint Traffic Awareness campaign conducted by MahaMetro, Traffic Police & PCMC at Nashik Phata, Dr. Ambedkar Chowk, Pimpri & Mahaveer Chowk, Chinchwad.
|
27 Aug 2018
|
Total 237 segments are launched for viaduct of PuneMetro Reach1 PCMC-Range Hills. 148 pillars with 69 pier caps are completed. 188 footings are done & excavation in progress. Also, pillar foundation work is in progress at Nashik Phata.
|
25 Aug 2018
|
Launching girder work in progress at Anand Nagar for PuneMetro Vanaz - Civil Court route along with piers for station. Foundation of pillars work now reached till More Vidyalaya. Pier caps ready near Krishna Hospital.
|
21 Aug 2018
|
PuneMetro Samvaad conduted at H. V. Desai College Mr. Limaye, Advisory Consultant & Mr. Rao explained various aspects about underground section, methods of construction.
|
15 Aug 2018
|
Inauguration of Information Center at Chattrapati Sambhaji Udyan at the hands of Lal Bahadur Shastri Primary School & differently-abled students with MahaMetro officials
|
14 Aug 2018
|
Twin trees, Entangled, 35-40 years old grown into V-Shape, transplanted successfully by MahaMetro
|
09 Aug 2018
|
Installation of 1st launching girder at Anand Nagar for PuneMetro Vanaz-Civil Court is in final stage.
|
08 Aug 2018
|
To make our roads safe, a Traffic awareness program was conducted by PuneMetro Traffic Management team at Bal Shikashan Mandir English Medium School.
|
07 Aug 2018
|
First span completed at Phugewadi near Mega Mart for PuneMetro Reach 1 PCMC- Range Hills with the help assembly of Ground Support Trestle while segment launching for 2nd span is in progress.
|
06 Aug 2018
|
1st RCC(Reinforced Cement Concrete) Girder is completed for PuneMetro stations at the newly developed casting yard at Kiwale for Reach 2 Vanaz-Civil Court
|
03 Aug 2018
|
Concreting of 1st pier arm for concourse level for Reach1 PCMC-Range Hills, Sant Tukaram Nagar PuneMetro station completed. Each pier will have 2 such arms for concourse & platform level.
|
01 Aug 2018
|
In short period 11 months PuneMetro casted over 1000 segments.
|
30 Jul 2018
|
5 trees from upcoming Sant Tukaram Nagar PuneMetro station location at Vallabhnagar, were transplanted at STP, Kasarwadi.
|
29 Jul 2018
|
PuneMetro station construction with Entry-Exit stair & escalator column casting for Reach2 started at Anand Nagar. Along with this, upcoming Ideal Colony station area is barricaded.
|
24 Jul 2018
|
MahaMetro team interacted with Mr. M. Deouskar, DRM Central_Railway -Pune Division & senior officials of Divisional Railway Manager Office
|
23 Jul 2018
|
78 more trees in PuneMetro alignment of Reach1 PCMC-Range Hills, between Nashik Phata to Vallabh Nagar bus stand are transplanted at STP, Kasarwadi.
|
20 Jul 2018
|
Viaduct work started at Phugewadi for PuneMetro Line 1 PCMC-Swargate.
|
18 Jul 2018
|
PuneMetro work has started at Bhosari near Nashik Phata for Reach1 PCMC-Range Hills. Piling operation started using a Piling Rig for piles to be inserted to support the formation of pillar foundation.
|
17 Jul 2018
|
3rd span of PuneMetro at Anand Nagar completed. Pier formation work for viaduct of Reach2 Vanaz-Civil Court is in progress. Soon a launching girder will be installed to speed up the work.
|
16 Jul 2018
|
Water discharged from Khadakwasala dam. PuneMetro work in riverbed is put on hold for some days. Total 102 piling completed near riverbed for Reach 2 with the help of piling rig. Footing for 24 piers completed, 23 piers ready till ground level, 3 piers ready till pier cap.
|
13 Jul 2018
|
Pune Metro hosted its Metro Samvaad, An Info series for citizen interaction & awareness.
|
11 Jul 2018
|
Pune Metro hosted its Metro Samvaad, An Info series for citizen interaction & awareness.
|
09 Jul 2018
|
Dr. Dixit, MD MahaMetro had a great discussion with French delegation from RE Department for Smart Cities led by Ambassador of France to India H.E. Mr. Ziegler.
|
05 Jul 2018
|
170 viaduct segments are ready & stacked for PuneMetro Reach2 Vanaz-Civil Court at casting yard near Wakad, 20 segments are already launched at Anand Nagar.
|
04 Jul 2018
|
Total 20 segments are launched for the formation of viaduct PuneMetro Reach2 Vanaz-Civil Court, 18 pillars with 7 pier caps are completed.
|
02 Jul 2018
|
Total 132 segments are erected for the formation of viaduct of PuneMetro Reach1 PCMC-Range Hills, 104 pillars with 50 pier caps are completed.
|
30 Jun 2018
|
Reach 1 PCMC-Range Hills 1st PuneMetro Sant Tukaram Nagars station Pier arm work in progress.
|
29 Jun 2018
|
PuneMetro underground metro work started at Swargate. Pilling operation & soil investigation is in progress.
|
18 Jun 2018
|
PuneMetro work progress for Reach 2 Vanaz-Civil Court will be implemented in phases, Pillars are getting ready near Ideal Colony, 18 segments are erected at Anand Nagar, 16 pillars with 4 pier caps are completed, 77 footings are done & excavation is going on for other pillars
|
18 Jun 2018
|
PuneMetro work progress for Reach 2 Vanaz-Civil Court will be implemented in phases, Pillars are getting ready near Ideal Colony, 18 segments are erected at Anand Nagar, 16 pillars with 4 pier caps are completed, 77 footings are done & excavation is going on for other pillars
|
15 Jun 2018
|
Formation of 12th span is in progress at Kharalwadi for PuneMetro Reach 1 PCMC-Range Hills viaduct. Total 115 segments are erected & approx. 6 to 10 segments get lifted per night.
|
11 Jun 2018
|
Second span of PuneMetro at Anand Nagar completed for Reach 2.
|
09 Jun 2018
|
GeoTech survey is in progress for tunneling to place the underground shaft at Swargate.Contractors with PuneMetro team conducted a site inspection.
|
06 Jun 2018
|
Site visit by Dr. Dixit, MD MahaMetro along with ED Mr. Ramnath & PuneMetro officials at upcoming Swargate underground metro station.
|
05 Jun 2018
|
On the occasion of WorldEnvironmentDay PuneMetro organized Tree Plantation Drive at ITI Aundh in presence of Dr. Brijesh Dixit, MD #MahaMetro, accompanied by MLA Mr. Vijay Kale, Mr. Ramnath, ED, Advisory Consultant Mr. Limaye, Principal Mr. Saygaonkar, Environmentalists & project team. Followed by an interaction with media.
|
05 Jun 2018
|
129 viaduct segment blocks ready & stacked at Wakad casting yard for PuneMetro Reach 2 Vanaz to Civil Court.
|
04 Jun 2018
|
10 Spans comprising of 99 segments ready at Kharalwadi for PuneMetro Reach 1. 89 pillars with 47 pier caps are completed. 161 footings are done.
|
31 May 2018
|
Piling operation using Piling Rig started near riverbed behind Chhatrapati Sambhajiraje Udyan for PuneMetro Reach 2.
|
29 May 2018
|
Traffic has diverted today 29th May near Kasarwadi for smooth traffic flow near ongoing PuneMetro Reach 1 work.
|
24 May 2018
|
PuneMetro work for Reach 1 PCMC - Range Hills is started at Harris Bridge too. Concrete footing for pillars is in progress with utmost care.
|
23 May 2018
|
605 viaduct segments are ready & stacked at casting yard for PuneMetro Reach 1 PCMC - Range Hills. Out of which 89 are launched at Kharalwadi to form 9 spans.
|
22 May 2018
|
3165 trees were planted last year & required care is being taken for them to survive & grow. Also total 167 trees are transplanted. This year plantation of around 6000 trees is planned.
|
21 May 2018
|
Trial Run of Traffic diversion near Kasarwadi.
|
19 May 2018
|
Pune Metro hosted its Metro Samvaad, An Info series for citizen interaction & awareness.
|
18 May 2018
|
Pune Metro hosted its Metro Samvaad, An Info series for citizen interaction & awareness.
|
17 May 2018
|
8 Spans comprising of 79 segments ready at Kharalwadi for PuneMetro Reach1 PCMC-Range Hills , 81 pillars with 46 pier caps are completed, 116 footings are done & excavation is going on for other pillars.
|
15 May 2018
|
Span of 9 segments is completed at Anand Nagar for Reach 2 Vanaz-Civil Court, 6 pillars & 3 pier caps are completed while work for other 21 in progress, 62 footings are done & excavation is going on for other pillars.
|
07 May 2018
|
Proposed alignment route for future extension of metro from Swargate to Katraj & from PCMC to Nigdi was surveyed by KfW bank officials along with Mr. Ramnath, Executive Director, PuneMetro & other officials.
|
06 May 2018
|
50 viaduct segments are ready & stacked at casting yard at Wakad for PuneMetro Reach 2 Vanaz to Civil Court.
|
05 May 2018
|
1st viaduct span for Reach 2 Vanaz to Civil Court completed.
|
02 May 2018
|
Along with the construction of other stations, erection of pillars for the proposed PuneMetro Sant Tukaram Nagar station is in progress.
|
02 May 2018
|
Footing for 22 columns at Sant Tukaram Nagar metro station for Reach 1 are completed and reinforcement & shuttering works are in progress
|
27 Apr 2018
|
PuneMetro work for Reach 2 Vanaz to Civil Court has gained the speed. First span at Anand Nagar is already in the end of completion. Total 51 footings are completed. Excavation work for the remaining pillars and also at Karve road are in progress.
|
23 Apr 2018
|
Site visit along the river bed by Dr. Brijesh Dixit, MD MahaMetro, with ED Mr. Ramnath & PuneMetro officials for proposed Deccan Gymkhana metro station
|
20 Apr 2018
|
Pune Metro hosted its Metro Samvaad, An Info series for citizen interaction & awareness.
|
17 Apr 2018
|
PuneMetro Reach 1 work begun near Harris bridge. For safety of citizens & to minimize inconvenience diversion has been planned.
|
15 Apr 2018
|
Seventh span is in completion stage at Kharalwadi for Reach 1 PCMC-Range Hills viaduct. Total 69 segments are erected. Along with this foundation for 111 piers, total 73 pillars and 43 Pier caps are completed.
|
15 Apr 2018
|
Formation of the 7th span is in progress at Kharalwadi for Reach 1 PCMC-Range Hills viaduct. Total 61 segments are erected along with this 40 Pier caps completed for PuneMetro.
|
12 Apr 2018
|
PuneMetro work for Reach 2 on the Karve road now started. Along with this one more segment has launched on the second pillar at Anand Nagar. Shuttering for two more pillars are also in progress.
|
09 Apr 2018
|
EOT(Electric Overhead Traveling) crane, Concrete Batching plant setup & 1st RCC(Reinforced Cement Concrete) girder is completed at casting yard, Kiwale for Reach 1 stations.
|
08 Apr 2018
|
Updates from casting yard near Nashik Phata. 438 viaduct segments are ready & stacked for PuneMetro Reach 1 PCMC - Range Hills.
|
06 Apr 2018
|
After getting the approval from Traffic Police the same day PuneMetro started barricading at Deccan corner for PuneMetro Reach 2.
|
02 Apr 2018
|
Site visit by Dr. Brijesh Dixit, MD MahaMetro along with ED Mr. Ramnath & PuneMetro officials at newly developed casting yard at Kiwale. Girders for stations of Reach 1 PCMC to Range Hills for concourse & platform level will be cast at this yard.
|
31 Mar 2018
|
125 trees were transplanted at different areas. It included Ashokas, Palm trees, two big trees, etc. They are transplanted at STP Plant Kasarwadi, Rose Garden, Akurdi, PCMC ground and Mutha river bed.
|
29 Mar 2018
|
Formation of span is in progress at Kharalwadi for Reach 1 PCMC-Range Hills viaduct. Total 40 segments are erected. Along with this foundation for 97 piers, total 61 pillars and 32 Pier caps are completed.
|
28 Mar 2018
|
Launching of first segment, 11 footings along riverbed & 22 footings at Paud road, total 33 footings of PuneMetro Reach 2 Vanaz-Civil Court has been completed
|
24 Mar 2018
|
10 months ago, Trees planted by Dr. Dixit, MD MahaMetro at Akurdi, Sector 29 are grown up & rooted well. Timely nurturing with required care is taken by dedicated Garden Dept of PuneMetro. Compound wall to prevent from cattle & other animals is built.
|
22 Mar 2018
|
For the construction of first Reach 1 PuneMetro station Sant Tukaram Nagar, total of 27 footings completed & shuttering work for columns has started.
|
20 Mar 2018
|
First viaduct segment launched at Anand Nagar for Reach 2 Vanaz to Civil Court
|
19 Mar 2018
|
Dr. Brijesh Dixit, MD, MahaMetro along with senior officials of PuneMetro visited Reach 2 site of Vanaz to Ramwadi route to inspect ongoing work of the 1st two pillars at Anand Nagar & reviewed the Traffic management.
|
16 Mar 2018
|
Pune Metro hosted its Metro Samvaad, An Info series for citizen interaction & awareness.
|
13 Mar 2018
|
Pune Metro hosted its Metro Samvaad, An Info series for citizen interaction & awareness.
|
12 Mar 2018
|
PuneMetro completed first two pillars for Reach 2 Vanaz to Civil Court at Anand Nagar.
|
11 Mar 2018
|
Pier cap concreting for 1st pillar at Kothrud is completed. Shuttering & foundation work for other pillars in progress. At the same time segment blocks are getting casting launching of viaduct
|
10 Mar 2018
|
As a part of National Safety Week campaign at PuneMetro, an emergency mock drill & training program on prevention of general fire & cooking fire was conducted for workers.
|
08 Mar 2018
|
PuneMetro officials along with 42 other employees donated blood with Akshay Blood Bank at our Sahayog Kendra, Near More Vidyalaya, Kothrud.
|
05 Mar 2018
|
47th National Safety Week celebration for the workers. PuneMetro has organized one week program for workers of both the routes & casting yards with the theme Reinforce Positive Behavior At The Workplace To Achieve Safety And Health goals.
|
05 Mar 2018
|
Piling operation started at Phugewadi PuneMetro station using a popular engineering machine a Piling Rig.
|
01 Mar 2018
|
2nd span of PuneMetro near Kharalwadi completed within a week. This is first span completed by Launching Girder.
|
01 Mar 2018
|
2nd span of PuneMetro near Kharalwadi completed within a week. This is first span completed by Launching Girder.
|
28 Feb 2018
|
Project progress of PuneMetro Reach 2 Vanaz-Civil Court: Shuttering for 2 pillars are partially completed, 16 footings are done & rest of places excavation is going on.
|
24 Feb 2018
|
Pune Metro hosted its Metro Samvaad, An Info series for citizen interaction & awareness.
|
23 Feb 2018
|
As of now the foundation for 88 piers, 50 pillars and 20 Pier caps are completed for Reach 1 PCMC-RangeHills
|
15 Feb 2018
|
Dr. Dixit, MD. MahaMetro, MLA Smt. Madhuritai Misal and Mr. Limaye, Advisory Consultant had a detailed discussion about decongestion of traffic and development of proposed multimodal integration hub at Swargate.
|
14 Feb 2018
|
By walk survey of underground section of PuneMetro from riverbed till Mandai by Dr. Dixit, MD MahaMetro & sr. officials.
|
14 Feb 2018
|
Pune Metro hosted its Metro Samvaad, An Info series for citizen interaction & awareness.
|
11 Feb 2018
|
PuneMetro commissioned its first launching girder at Kharalwadi for Reach 1 PCMC-RangeHill.
|
10 Feb 2018
|
Foundation for 9 pillars is completed for station at Sant Tukaram Nagar. GeoTech survey for other stations in progress & work will start soon.
|
09 Feb 2018
|
158 viaduct segments are ready & stacked near Nashik Phata casting yard for Reach 1 PCMC - Range Hills.
|
04 Feb 2018
|
PuneMetro work for Reach 1 PCMC-Range Hills has gained good speed. Till now foundation for 79 pillars, total 41 pillars and 12 Pillars cap are completed.
|
03 Feb 2018
|
Pune Metro hosted its Metro Samvaad, An Info series for citizen interaction & awareness.
|
01 Feb 2018
|
To avoid traffic from SNDT college to Deccan during construction work, PuneMetro team has started road widening wherever required. It will not affect any tree.
|
26 Jan 2018
|
Flag hoisting by MahaMetro team at PuneMetros Phugewadi office on RepublicDay
|
25 Jan 2018
|
2 footings at river bed and 6 footings at Vanaz so total 8 footings are completed. Also shuttering for first pillar and excavation work for the remaining pillars are in progress.
|
23 Jan 2018
|
PuneMetro organized prize distribution ceremony for all the winners on the 1st anniversary of incorporation of Maharashtra Metro Rail Corporation Ltd.
|
23 Jan 2018
|
Special panel discussion organized by PuneMetro to celebrate 1st Anniversary of incorporation of MahaMetro.
|
21 Jan 2018
|
Dr. Brijesh Dixit, MD, MahaMetro interacted with the citizens at Vasantotsav 2018
|
20 Jan 2018
|
Essay writing & Drawing competition organized by MahaMetro as a part of our 1st Anniversary celebration at govt schools, Netaji Subhaschandra Bose School, Yerawada, PMC & PCMC Primary School, Kharalwadi.
|
19 Jan 2018
|
MahaMetros Cleanliness drive at Mutha riverbed. A small contribution towards Clean India by PuneMetro team & cleaned 1.45 KM riverbed part along the ongoing work of the proposed route. Over 250 garbage bags filled.
|
18 Jan 2018
|
French Development Agency & European Investment Bank were on appraisal mission of PuneMetro. Ongoing progress was reviewed.
|
18 Jan 2018
|
Bhoomipujan of the Sant Tukaram Nagar station of PuneMetro was performed by Hon. Guardian Minister
|
16 Jan 2018
|
PuneMetro team completed first viaduct span for Reach 1 PCMC-Range Hills.
|
15 Jan 2018
|
Names of the winners of the slogan contest are declared
|
15 Jan 2018
|
PuneMetro has completed the footing of the first pillar at river bed near Deccan for Reach 2 Vanaz to Civil Court.
|
13 Jan 2018
|
PuneMetro team of Reach 2 celebrated the Road Safety Week at Paud road.
|
10 Jan 2018
|
MoU signed between Dr. Brijesh Dixit, MD MahaMetro, Mrs. Prerna Deshbhratar, Addl Municipal Commissioner(Spl), PMC and Mr Kong Wy Mun, CEO, Singapore Cooperation Enterprise for the Urban Management(Multi-Modal Transport) during a program at Yashada, Pune.
|
09 Jan 2018
|
Second Casting Yard for PuneMetro is developed in Marunji near Bhumkar Chowk. Along with the erection of pillar at Vanaz route segment formation is also started at casting yard.
|
09 Jan 2018
|
Second Viaduct Segment installed and aligned successfully at Kharalwadi for Reach 1 PCMC-Range Hills.
|
08 Jan 2018
|
PuneMetro organised slogan contest for all.
|
04 Jan 2018
|
For Reach 1 Pimpri to Range Hills more than 50 pillars work is in progress. , Total 72 segments are formed for 3 spans at Casting Yard near Nashik Phata. 6 Gantry cranes will be erected for lifting & shifting of segments. Out of which 4 are already erected & work for other 2 is in progress.
|
24 Dec 2017
|
Pune Metro completed one year. On this day, today, Hon. PM. Shri Narendra Modiji along with Hon. CM. Shri Devendra Fadnavisji laid the foundation stone of MahaMetro Pune Metro Rail Project at a historic event.
|
23 Dec 2017
|
MahaMetro organized Safety Award function for workers who did excellent work for PuneMetro Reach 2.
|
22 Dec 2017
|
Video conference by Dr. Brijesh Dixit, MD. MahaMetro with media.
|
21 Dec 2017
|
Footing work for 2nd pillar is done at Vanaz route and shuttering for the 1st pillar is in progress along with excavation for other pillars.
|
18 Dec 2017
|
Pune Metro hosted its Metro Samvaad, An Info series for citizen interaction & awareness.
|
14 Dec 2017
|
The first via duct segment of Pune Metro project was launched in the morning between Pier P349 to P348 through ground launching system near Kharalwadi.
|
12 Dec 2017
|
Maha Metro Pune Rail Project Signs Agreement with Bureau Veritas India Limited for setting up Material testing laboratory
|
09 Dec 2017
|
5 trees were transplanted from Bhosari to behind the PuneMetro Sahayog Kendra at Vallabhnagar.
|
02 Dec 2017
|
Safety leaflet was released by Dr. Dixit, MD. MahaMetro for labourers safety.
|
02 Dec 2017
|
Press conference addressed by Dr. Brijesh Dixit MD MahaMetro at Vallabh Nagar to inform that first Metro station to come up at Sant Tukaram Nagar, Pimpri
|
28 Nov 2017
|
MahaMetros Quick Response Team(QRT) formed & deployed for Vanaz to Civil Court route of PuneMetro.
|
26 Nov 2017
|
Foundation of first Pier near Vanaz for Vanaz to Ramwadi corridor 2 of Pune Metro is done.
|
19 Nov 2017
|
By walk survey of entire alignment of PuneMetro from Ramvadi to Shivajinagar by Dr. Brijesh Dixit, MD MahaMetro & senior officials.
|
18 Nov 2017
|
PuneMetros 1st Sahayog Kendra inaugurated at Vallabh Nagar at hands of Dr.Dixit, MD, MahaMetro
|
18 Nov 2017
|
Site visit by Dr. Dixit, MD MahaMetro along with ED Mr. Ramnath & PuneMetro officials at Shivajinagar Grain Godown.
|
13 Nov 2017
|
First Sahayog Kendra of PuneMetro at Vallabh Nagar behind ST Station, Pimpri. A Toll-free number is 18002705501
|
13 Nov 2017
|
MahaMetros second pillar for PuneMetro stands at Kharalwadi.
|
12 Nov 2017
|
Along with Nashik Phata-Kharalwadi, PuneMetro work has started at Phugewadi also from CME gate to Megamart. Concrete footing for 6 piers and 15 PCF(Plane concrete footing) are completed.
|
09 Nov 2017
|
Pune Metro hosted its Metro Samvaad, An Info series for citizen interaction & awareness.
|
07 Nov 2017
|
Geotechnical survey along the riverside in progress for PuneMetro’s Vanaz to Ramwadi route.
|
06 Nov 2017
|
MahaMetro got the first prize for the best urban mobility project at the UMI international expo. and conf. held at Hyderabad from 4 Nov to 6 Nov.
|
27 Oct 2017
|
MahaMetro has received possession of Food Grain Godown land from Government located at Shivajinagar for Inter-Change Station
|
24 Oct 2017
|
PuneMetro 1st pillar completed near Nashik Phata
|
18 Oct 2017
|
PuneMetro organised an event "Suprabhat te Good Morning" at M.E,S. auditorium, Kothrud and Bharatnatya Mandir, Pune. A melodious music was enjoyed by the citizens.
|
16 Oct 2017
|
Boards are erected to inform that Nashik Phata to Kharalwadi grade separator road to be closed for specific time for PuneMetro Viaduct work.
|
08 Oct 2017
|
"Know our Metro" - An interactive session with citizens organized by Standing Committee Chairman, PMC Mr. Murlidhar Mohod, took place at Yashwantrao Chavan Natyagruha. Very illustrative presentation by Mr. Limaye also Mr. Subramaniam, ED clarified many doubts of the citizens.
|
05 Oct 2017
|
Dr. Dixit, MD. MahaMetro & PuneMetro team conducted site inspection of ongoing excavation work near Vanaz route & reviewed traffic situation
|
28 Sep 2017
|
Inauguration of civil work of #PuneMetro Corridor-2 Vanaz-Civil Court at the hands of Hon. Guardian Minister Shri Girishji Bapat along with Hon. Mayor Smt. Mukta Tilak, Hon. MLA Smt. Medha Kulkarni and all corporators.
|
28 Sep 2017
|
Pune Metro work has started from Paud Road near Vanaz.
|
25 Sep 2017
|
Dr. Dixit MD. #MahaMetro & #PuneMetro team interacted with Hon. Mayor Smt. Mukta Tilak, Commissioner Kunal Kumar, PMC & all corporators.
|
14 Sep 2017
|
Along with the shuttering of first pillar construction of other pillars are in progress. Work reached to Kharalwadi.
|
11 Sep 2017
|
Geotechnical survey is in progress near PCMC building.
|
05 Sep 2017
|
Safety toolbox meeting conducted daily at casting yard near Nashik Phata.
|
01 Sep 2017
|
Foundation of 10th Pillar of PuneMetro at Kharalwadi is in progress.
|
01 Sep 2017
|
Making of Precast Concrete Girders used in construction of viaducts has started at newly developed casting yard near Nashik Phata
|
24 Aug 2017
|
Plate Load Test at Kharalwadi near Hindustan Antibiotics to determine Safe Bearing Capacity of soil used for foundation design in progress
|
24 Aug 2017
|
7 pillars work for Reach 1 are in progress.
|
19 Aug 2017
|
PuneMetro office inaugurated at Ghole Road Museum at the hands of Hon. Guardian Minister Shri. Girishji Bapat with Dr. Dixit, MD, MahaMetro.
|
10 Aug 2017
|
Site visit by AFD and Pune Metro team for underground route.
|
09 Aug 2017
|
Site visit by AFD french with Pune Metro team.
|
09 Aug 2017
|
Press conference addressed by Dr. Dixit, MD, MahaMetro and French Development Bank (AFD) delegation consisting of Mr. Nicholas, Director
|
08 Aug 2017
|
PuneMetro shuttering work on 1st pier near Nashik phata & work on next pillars are in progress.
|
07 Aug 2017
|
PuneMetro team visited SOFOSH Shreevatsa Child care center. Tied Rakhi & joyful time spent on RakshaBandhan.
|
05 Aug 2017
|
Pune Metro team conducted Samvaad at Khadki Education Society.
|
27 Jul 2017
|
PuneMetro team completed the concrete footing of second Pillar at Kasarwadi for Reach 1. Third & fourth Pillars work is in full swing.
|
25 Jul 2017
|
Traffic Diversion today: Maha Metro used solar powered digital signboards near Nashik phata for PuneMetro to display safety signs & alert messages
|
21 Jul 2017
|
Boards with Pune Metro route map with respective station names started installing for citizen information at Reach 1 and at Reach 2
|
21 Jul 2017
|
Press conf. addressed by PuneMetro team, Prof. Rawal, CoEP & AC traffic police, Mr. R. Bhamre at upcoming Metro office, Phugewadi.
|
20 Jul 2017
|
Maha Metro will discuss with traffic police to divert vehicle from BRTS and service road with the help of #CoEP who has given traffic diversion plan.
|
13 Jul 2017
|
Topography survey for PuneMetro depot & underground route at agriculture college is started.
|
12 Jul 2017
|
Dr. Brijesh Dixit, MD MahaMetro along with PuneMetro team inspected 1st pillar site work near Nashik phata and reviewed traffic management
|
12 Jul 2017
|
Dr. Dixit, MD. MahaMetro along with PuneMetro team addressing the press conference at PCMC
|
09 Jul 2017
|
Concrete footing for 1st pillar of PuneMetro done near Nashik phata.
|
04 Jul 2017
|
Dr. Dixit, MD MahaMetro had a special interaction session with Public Relations Council of India, Pune Chapter.
|
03 Jul 2017
|
Dr. Dixit, MD MAhaMetro addressing the press at Patrakar Bhavan.
|
03 Jul 2017
|
PuneMetro "Metro Van-Vihar" at Taljai Hill, Pachgaon Parvati. Tree plantation drive in presence of Dr. Brijesh Dixit, MD MahaMetro
|
30 Jun 2017
|
Foundation of PuneMetro 1st pillar near Nashik phata progressing as planned & excavation for next 2 pillars started
|
24 Jun 2017
|
PuneMetro team enlightened about Pune metro to the members of Pune International Centre at Mangaldas road, PIC Adda.
|
22 Jun 2017
|
PuneMetro started civil work for foundation of the first pillar
|
20 Jun 2017
|
Pune Metro team interacted with Corporators at PCMC General Body Meeting.
|
17 Jun 2017
|
Dr. Dixit, MD MahaMetro Site visit on Reach 1. Instructioned to speed up work & to ensure adequate safety precautions during rains suggested
|
17 Jun 2017
|
Pune Metro hosted its 5th Metro Samvaad at Nigdi, An Info series for citizen interaction & awareness.
|
13 Jun 2017
|
Maharashtra Cabinet approves the draft MoU Phase 1 of Pune Metro Rail Project.
|
05 Jun 2017
|
Tree plantation drive by Dr. Brijesh Dixit, MD MahaMetro and PuneMetro team at Sector 29, Akurdi on World Environment Day.
|
05 Jun 2017
|
SolarPulse One- battery operated vehicle as a part of feeder services for last mile connectivity, Launched by Dr. Brijesh Dixit.
|
01 Jun 2017
|
Civil work started at Nashik phata. Excavation is started
|
01 Jun 2017
|
GeoTech investigation on Muttha river bed started for PuneMetro.
|
25 May 2017
|
Barricades are erected on road at Nashik Phata for civil work.
|
17 May 2017
|
Expert committee & senior officials team of MahaMetro reviewed the alignment routes of underground stations of PuneMetro rail project.
|
06 May 2017
|
Geo-technical survey for underground metro station is in progress at Bharati apartment, Shivaji Nagar
|
27 Apr 2017
|
In 120 days, DGPS - 100%, Topography - 94% and GeoTech - 82%
|
13 Apr 2017
|
Site visit by Dr. Dixit at agriculture college depot, Hingane, Khadakwasla Dam, Akurdi, Swargate
|
13 Apr 2017
|
Tender for a 10.75-km elevated stretch from Pimpri Chinchwad to Range Hills is opened.
|
11 Apr 2017
|
Pune Metro hosted its 4th Metro Samvaad, An Info series for citizen interaction & awareness.
|
07 Apr 2017
|
Second tender is issued. This is for 7.150 Kms elevated stretch from Vanaz to Civil Court.
|
22 Mar 2017
|
Pune Metro hosted its 3rd Metro Samvaad, An Info series for citizen interaction & awareness.
|
15 Mar 2017
|
75% of GeoTech work completed.
|
12 Mar 2017
|
Dr. Dixit, MD MahaMetro met HRD Minister Hon. Prakash Javadekarji. Discussed about PuneMetro station designs, alignment and other important aspects.
|
27 Feb 2017
|
The first of the tenders for the project are out. These are for a 10.75-km elevated stretch from Pimpri Chinchwad to Range Hills.
|
20 Feb 2017
|
51% of Geo Technical work completed.
|
03 Feb 2017
|
Pune Metro hosted its 2nd Metro Samvaad, An Info series for citizen interaction & awareness.
|
25 Jan 2017
|
Press conference addressed by Dr. Brijesh Dixit MD MahaMetro after incorporation & shared his views about the way forward for Pune Metro.
|
23 Jan 2017
|
Incorporation of Maharashtra Metro Rail Corporation Limited (MAHAMETRO), with 50:50 JV of Government of India and Government of Maharashtra
|
21 Jan 2017
|
Pune Metro hosted its 1st Metro Samvaad, An Info series for citizen interaction & awareness.
|
19 Jan 2017
|
Supreme Court stays NGT order refraining MahaMetro from carrying out civil work on the river bed stretch of 1.7 km
|
08 Jan 2017
|
An expert & senior officials team reviewed the alignment routes of Pune Metro.
|
29 Dec 2016
|
Pune Metro review meeting held at metro office with Shri Girish Bapat BJP, Mr. Brijesh Dixit, MD, Mr. Ramnath, Ex. Director, MahaMetro
|
29 Dec 2016
|
Press conference at Pune Metro new office at Koregaon Park road, addressed by Mr. Brijesh Dixit, MD. Introduced website & social media channels . Mr. Dixit, explained results of Geo-technical survey in form of rock samples.
|
25 Dec 2016
|
Soil testing & topographical surveys start..
|
24 Dec 2016
|
Land survey continued the other morning, and a historical bhoomi pujan event took place(YouTube or Twitter Link of video).
|
23 Dec 2016
|
Mr. Brijesh Dixit, surveyed various routes in both the corridors with his team .
|
16 Dec 2016
|
Mr. Brijesh Dixit, MD, Maha Metro Arrives in the city. Meets the Commissioner of PMC and holds a join press conference.
|
12 Dec 2016
|
Architect finalized for setting up the office, land surveys started for casting yards
|
10 Dec 2016
|
Project Director, NMRCL forms a team to review the DPR, and define a plan of action.
|
09 Dec 2016
|
Team of 5 key people from NMRCL, Nagpur Arrived in the city. Office location finalized and Bhoomipujan date decided as 24th December
|
08 Dec 2016
|
Pune Metro Project Approved by cabinet chaired by Hon. PM Shri Narendra Modi
|