PCMC to NIGDI Civil Work Status

Progress status as on 15/06/2026

Design and Construction of Elevated Viaduct of Length 4.519 Kms from CH:(-1079.899m to CH:(-) 5599.298m between PCMC and Nigdi (Bhakti Shakti) on the North-South Corridor of Pune Metro Rail Project – Reach-1 Extension )
S.No. Activities Unit Total Scope Achieved Till Date
1 Open foundation Nos 153 131
2 Pier Nos 153 124
3 Segment Casting Nos 1329 972